(a) A contractor may not assert a claim of breach of contract by the Commission under Texas Government Code, Chapter 2260, unless the contractor complies with each of the following requirements:
(1) the contractor shall deliver a written notice of the claim to the Director by hand, certified mail return receipt requested, or other verifiable delivery service;
(2) the contractor or the contractor's authorized representative shall sign the notice.
(3) The written notice shall state in detail:
(4) The contractor shall deliver the notice of claim no later than 180 days after the date of the event that the contractor asserts as the basis of the claim.
(b) In addition to the mandatory contents of the notice of claim as required by this section, the contractor may submit supporting documentation or other tangible evidence to facilitate the Commission's evaluation of the contractor's claim.
Source Note: The provisions of this §20.31 adopted to be effective February 12, 2004, 29 TexReg 1196